You asked three contractors to bid the same kitchen, and the numbers came back at $68,000, $91,000 and $114,000. It is tempting to assume the middle number is the fair one, or that the low bid is a bargain. In most cases the three contractors are not pricing the same project at all. One left out the permit, one assumed you would buy your own appliances, and one priced custom cabinets while the others priced semi-custom.
Comparing remodeling bids is really about turning three different documents into one apples-to-apples picture. This guide walks through how we recommend Los Angeles homeowners do that, line by line, before signing anything.
Key Takeaways
- A bid is only comparable when every contractor prices the same written scope of work. Send all bidders the same scope sheet or drawings.
- Allowances, exclusions and “by owner” items explain most of the gap between a low bid and a high bid.
- Check the license, insurance and workers’ compensation status of every bidder on the CSLB website before you compare prices.
- In California, the down payment on a home improvement contract cannot exceed 10 percent of the price or $1,000, whichever is less.
- The lowest number is often the most expensive project once change orders start. Price the risk, not just the total.
Why Do Remodeling Bids Vary So Much?
Labor rates and overhead differ between companies, but those differences rarely explain a 40 percent spread. The bigger reasons are almost always on paper:
- Different scopes. One contractor includes moving a wall and upgrading the electrical panel. Another assumes the wall stays and the panel is fine.
- Different allowances. A $3,000 tile allowance and a $9,000 tile allowance produce very different totals, even if the labor is identical.
- Different assumptions about the house. An experienced remodeler who knows how 1950s Valley homes are wired may include money for updating circuits. A less experienced one may not mention it until the walls are open.
- Different levels of project management. A bid that includes a dedicated project manager, daily cleanup, dust protection and a site toilet costs more than one that does not.
The fix is to control the inputs. Before you request bids, write a one or two page scope sheet that lists every room, every change and every finish level you want. If you have architectural drawings, send the same set to everyone. Then ask each contractor to price that exact scope and list anything they would do differently as a separate option.
What Should Every Remodeling Bid Include?
A bid you can actually compare will break the job into parts. At a minimum, look for these line items:
- Demolition and haul-away, including disposal fees
- Framing and structural work, with any engineering called out
- Electrical, plumbing and HVAC, each listed separately
- Insulation, drywall and texture
- Cabinets, countertops, tile, flooring and fixtures, either as firm prices or as allowances
- Painting and finish carpentry
- Permits, plan check fees and inspections
- Site protection, cleanup and final cleaning
- Schedule, with an estimated start date and duration
- Payment schedule tied to completed work
If a bid is one line that says “Kitchen remodel, complete, $74,500,” ask for a breakdown. A contractor who cannot tell you what the electrical portion costs probably has not thought it through yet, and that is where surprises come from.
How to Build a Side-by-Side Bid Comparison
Put the bids into a simple spreadsheet or table with one row per line item and one column per contractor. Fill in what each one includes, and mark anything missing as “not included.” A filled-in comparison often looks something like this:
| Line item | Contractor A | Contractor B | Contractor C |
|---|---|---|---|
| Permits and plan check | Included | By owner | Included |
| Cabinets | Allowance $14,000 | Allowance $22,000 | Firm price, semi-custom |
| Tile allowance | $4 per sq ft | $12 per sq ft | $8 per sq ft |
| Electrical panel upgrade | Not included | Included | Option, priced separately |
| Drywall repair outside kitchen | Not included | Included | Included |
| Debris removal | Included | Included | Included |
| Estimated duration | 6 weeks | 10 weeks | 9 weeks |
Once every row is filled in, adjust the low bids upward for the items they left out. It is common for the “cheapest” bid to land in the middle once permits, a realistic tile allowance and the panel upgrade are added back in.
How Do Allowances Work, and How Can They Mislead You?
An allowance is a placeholder budget for an item you have not selected yet, such as tile, light fixtures or plumbing trim. If you pick something that costs more than the allowance, you pay the difference. If you pick something cheaper, you should get a credit.
Allowances are useful, but they are also the easiest place to make a bid look smaller than it is. A $1,500 allowance for a full set of kitchen light fixtures, faucet and sink will not cover what most homeowners actually choose. Before comparing totals, do two things:
- Ask every contractor to use the same allowance amounts, or replace their allowances with yours.
- Ask whether the allowance covers material only, or material plus installation. Some contractors add labor on top of overages, which matters if you upgrade.
The best way to avoid allowance surprises is to choose as many finishes as possible before you sign. That also helps with ordering, since items like custom cabinets and special-order tile can take weeks to arrive.
Which Exclusions Should You Look For?
Read the exclusions section of every bid twice. These are the items most often excluded or left vague:
- Permit fees and plan check fees
- Architectural drawings, structural engineering and Title 24 energy reports
- Asbestos or lead testing and abatement in older homes
- Repairs to hidden damage such as rot, termite damage or failed plumbing
- Electrical service or panel upgrades
- Patching and painting areas outside the work zone
- Appliance installation or hookups
- Final cleaning
Exclusions are not automatically a red flag. Some items genuinely cannot be priced until the walls are open. What matters is that you know about them in advance and set aside a contingency for them. For most remodels of older Los Angeles homes, a contingency of 10 to 15 percent of the construction cost is a sensible starting point.
How Do You Check the Contractor Behind the Number?
A bid is only as good as the company standing behind it. Before you spend time comparing prices, verify each bidder:
- License. Look up the license on the CSLB license check. Confirm the name, the license classification and that it is active. Under California law, anyone doing home improvement work valued at $1,000 or more in combined labor and materials must be licensed.
- Workers’ compensation. The same CSLB page shows whether the company has workers’ comp on file or claims an exemption. If a crew will be working in your home, an exemption deserves a question.
- Liability insurance. Ask for a certificate of insurance.
- References and recent work. Ask for two or three clients with projects similar to yours, ideally in the last two years.
Our article on questions to ask a remodeling contractor before hiring covers the interview side of this in more detail.
What Payment Terms Are Normal in California?
The payment schedule tells you a lot about a contractor. California’s Contractors State License Board states that the down payment on a home improvement contract should never exceed 10 percent of the contract price or $1,000, whichever is less. After that, payments should follow completed work, not get ahead of it.
A healthy schedule ties each payment to a milestone you can see, such as “rough plumbing and electrical inspected” or “cabinets installed.” Be cautious if a bid asks for large payments for materials before anything has been delivered, or for most of the money before the project is half done.
Red Flags When Comparing Bids
- A price far below the others with no clear explanation
- Pressure to sign the same day, or a “discount” that expires tomorrow
- A request for cash, or for a down payment above the legal limit
- Suggestions to skip the permit to save money or time
- No written scope, or a scope that says “per conversation with owner”
- A license number that does not match the company name on the bid
Skipping permits can follow you for years, especially when you sell. We explain why in what happens if you remodel without a permit.
Frequently Asked Questions
How many remodeling bids should I get?
Three is the number most homeowners and the CSLB use as a rule of thumb. Fewer than three makes it hard to tell what is normal. More than four usually adds time without adding much insight, as long as the scope you sent is clear.
Should I always throw out the lowest bid?
No. Throw out bids you cannot explain. If the low bid is low because the contractor has lower overhead or already has your cabinet line in stock, it may be a good choice. If it is low because it leaves out permits and uses unrealistic allowances, it is not really lower.
Is it fair to share one contractor’s price with another?
Sharing totals to start a bidding war tends to backfire, because contractors respond by cutting scope or quality rather than margin. It is reasonable, though, to ask a contractor why their number for a specific item, such as electrical, is much higher than another bid you received.
What is the difference between an estimate and a bid?
An estimate is a rough range based on limited information, often given at the first site visit. A bid is a detailed price for a defined scope that the contractor is prepared to put into a contract. Only bids should be compared line by line.
How long should a remodeling bid take to prepare?
For a bathroom, a week or two is common. For a kitchen, addition or whole-home remodel with drawings, two to four weeks is normal because subcontractors and suppliers need to price their parts. A detailed bid that arrives quickly is fine, but a one-line number delivered the same afternoon usually means little real pricing was done.
Can I negotiate a remodeling bid?
Yes, but negotiate scope rather than just price. Choosing a stock cabinet line, keeping plumbing in place or phasing part of the work can lower the total without asking the contractor to cut corners. Our guide to reducing remodeling costs without cutting quality has more ideas.
Conclusion
Comparing remodeling bids well takes an afternoon with a spreadsheet, and it can save you thousands of dollars and months of frustration. Send every contractor the same scope, line up the bids item by item, add back what the low bids left out and check the people behind the numbers. The bid that is clearest, most complete and most realistic is usually the one that finishes closest to its original price.